The government-funded footbridge project is under the Coffee Industry Corporation's Coffee Access Road Project with an investment of K529,000.00. According to Chief Executive Officer (CEO) Charles Dambui the project span was for three months however he was pleased that the footbridge was completed in 2 months. 'This is an impact project for the local people in the Maril-Minimbi area and we are very happy that this has taken less time to complete it by the contractor Rumaris Investment Ltd.' Managing Director of Rumaris Investment Ltd, Benson Rumbai thanked the government through CIC for realising the need of the people in the area and enabling the project to come to its completion.