Chances are you have heard of the Bataan-Cavite Interlink Bridge, which is described as a cable-stayed bridge with the goal of reducing travel time from Bataan to Cavite from the five hours it currently takes, to 40 minutes when the bridge is done. It was supposed to have been completed by January 2022 at a cost of $3.6 billion. The National Economic Development Authority approved the project in January 2020, construction was supposed to begin in November 2020, you get the picture. As it turns out, as of March this year, the 'detailed engineering design of the project … is still ongoing, but it's now at a substantial 70 percent.