Crews complete construction of Bailey bridge
newscatcher
2023-05-04 02:34
Crews complete construction of Bailey bridge
A Downer crew of six men took 61 hours to complete the 49m Bailey bridge across the Waikare River. They started last Wednesday on the bridge proper, but work began early in April preparing the ground around the site. Two piers had to be constructed to support the bridge. Two of the team were on site yesterday to finish off the job, screwing down the deck, while the rest went on to Whanawhana, inland from Napier to make a start on a Bailey bridge there. Waka Kotahi NZ Transport Agency controls New Zealand's stocks of Bailey bridges which are stored at Downer depots in Hawke's Bay and Christchurch.