15 SABAH PAN BORNEO HIGHWAY PROJECT PHASE 1 PACKAGES TO BE READY BY JANUARY 2025
PAPAR, Aug 20 (Bernama) -- A total of 15 work packages in Phase 1 of the Sabah Pan Borneo Highway Project (LPB) are now at 82 per cent of construction and scheduled to be fully completed in January 2025, said Works Minister Datuk Seri Alexander Nanta Linggi. He said three of the 15 packages are now fully completed and can be used. "For the 19 Phase 1B packages... the packages that have not yet started and are expected to be tendered in the fourth quarter of 2023, after the Value Management Laboratory is finalised," he told reporters after a working visit to the Donggongon Road Upgrade project site to Papar Spurs Phase 2 and 3 and Work Package 04 (Bongawan to Papar) of the Sabah LPB here today.